Background
The Alligator River NWR encompasses about 154,000 acres on the Albemarle Peninsula in North Carolina. The primary climate change impact of concern to the refuge and the whole of the Albemarle Peninsula is sea level rise. In 2010, models showed that up to 469,000 acres of the peninsula could be flooded with a 12-inch rise in sea level, and nearly 750,000 acres could be flooded with a 20-inch rise. This vulnerability is exacerbated by human alterations to the system, including an extensive network of drainage ditches used for agriculture and forestry. Sea level rise will intensify other coastal problems such as shoreline erosion, saltwater intrusion, and biodiversity loss. TNC and USFWS worked together to test three adaptive management strategies at the Point Peter demonstration site on the refuge to determine which approaches would enhance the resilience of the ecosystem.
The three adaptation strategies included:
- Using oyster reefs to dissipate wave energy, slow currents, and reduce shoreline erosion. An added benefit is that these reefs help in carbon sequestration and provide habitat for a variety of species.
- Using water control structures equipped with flashboard risers and tide gates to restore the hydrologic regime and prevent saltwater intrusion.
- Planting salt- and flood-tolerant vegetation like bald cypress and black gum to enhance future shoreline stability and combat expected biodiversity and habitat loss. In addition, the project leads worked to establish migration corridors for species to move inland and upland from low lying areas.
Implementation
Several of the adaptation strategies required federal and state permits. Because the refuge is located in a wetland environment, USFWS had to acquire a permit through the Army Corps of Engineers. In addition, permits were required through the state’s Coastal Area Management Act (CAMA) for any activities happening in Pamlico Sound (i.e. oyster reef construction). This state permitting process caused some problems for the project because most of CAMA’s rules are very specific to shoreline development, but not to coastal restoration efforts. Because the materials used to construct the oyster reef did not conform to CAMA’s idea of fill material, the permit was elevated to a “major permit” and it turned into an eight-month process before it was finally approved.
This project was supported by a $1 million donation from Duke Energy, a $250,000 private donation, a Southeast Aquatic Resources Partnership Community-based Restoration Program grant, a NOAA Community-based Restoration Program grant, and several other smaller donations.
Marl (calcium carbonate fossil rock) was used to construct oyster reefs to buffer the shoreline, water control structures were strategically placed in areas to restore the region back to a sheet flow system, and test plots of salt-and flood-tolerant species were planted. Monitoring by two TNC staff members, with the assistance of several interns, took place for all three strategies:
- Oyster Restoration: examining shoreline erosion rates, spat recruitment, faunal usage, water quality
- Hydrologic Restoration: water control structures and measuring water quality and flow within the ditches to figure out flow speed and direction, location of salt wedges
- Vegetative Restoration: monitoring growth and survivability of salt- and flood-tolerant vegetation species; investigating how to monitor peat accumulation after the restoration of flow
The project managers engaged with local communities, fishermen, NGOs, state and federal agencies, and the general public to educate them on the project through public meetings, volunteer involvement, a sign at the demonstration project area for refuge visitors, and a fact sheet.
Citation
Gregg, R.M. and Braddock, K.N. (2021). Alligator River National Wildlife Refuge/Albemarle-Pamlico Peninsula Climate Adaptation Project [Case study on a project of The Nature Conservancy - Nags Head Woods and the U.S. Fish and Wildlife Service - North Carolina]. Version 2.0. Product of EcoAdapt's State of Adaptation Program. Retrieved from CAKE: https://www.cakex.org/case-studies/alligator-river-national-wildlife-refugealbemarle-pamlico-peninsula-climate-adaptation-project (Last updated April 2021)